At the end of March 2014 it was announced that Russia’s
Lukoil began producing oil at its West Qurna 2 field. The company originally
won a contract for the field in 2009, but ran into a series of delays, which
set back its work for two years. Those problems included having to demine the
area it was operating in, disputes with local tribes, late contracts, and its
partner Norway’s Statoil pulling out of the deal. Lukoil eventually overcame those
situations, but its difficulties may not be over as Iraq’s oil export
infrastructure may provide more hold-ups.
Last month West Qurna 2 finally began pumping
oil. By the end of March 2014 it was up to 120,000 barrels a day. Oil Minister
Abdul Karim Luaibi told the press that he was hoping that it would reach
400,000 barrels by the end of the year. The field is run by Russia’s Lukoil,
and has a final target of 1.2 million barrels a day. West Qurna 2 is a crucial
part in Baghdad’s plan to reach 4 million barrels in total production in 2014.
Iraq pumped 3.5 million barrels in February. One barrier standing in the way of
achieving that goal is the fact that Iraq is behind in renovating and expanding
its export infrastructure. The result is that any time there is a reduction in
exports the Oil Ministry often has to cut back production because there is not
enough capacity to store the excess. That is one reason why Iraq has never met
its goals with regards to its petroleum industry, because it simply doesn’t
have the equipment to pump as much as it wants. It also means the Ministry may not be able to handle West Qurna's output when it really gets up and running.
West Qurna 2 has already faced its own share of problems.
Lukoil won the contract for the field in December
2009. It was originally partnered with Norway’s Statoil Hydro that held 15%
of the contract. The two agreed to a final production level of 1.8 million
barrels a day and remuneration fee of $1.15 per barrel. Drilling at the field
was supposed to start
in 2011 and production in 2012. Those goals were continuously pushed back.
In April 2011 Lukoil announced that it had fallen
behind schedule. By January 2012 Lukoil said that production would not
start until
January 2013. Then when that year rolled around the company revised its timeline
again to the end of the year,
then to the start
of 2014, before aiming
for the spring. These constant changes did not make Baghdad happy, and by December 2013, the Oil
Ministry went to the company to demand that it speed up its work and get the
field on line sooner rather than later. At the same time, Lukoil was able to
renegotiate its contract to reduce
its ultimate production goal down from 1.8 million barrels to 1.2 million
in December 2012.
The cause of the delays was not all under Lukoil’s control.
First, the area around the field had to be extensively de-mined.
Most of this ordinance dated back to the Iran-Iraq War of the 1980s. Removing
the mines started in 2010, and was still an issue by
the end of the following year causing the first of many hold-ups for Lukoil
and Statoil. Second, local
tribes complained, protested, and attacked the oil companies demanding
compensation for their land that was being taken for the development of the
field and jobs for their followers. In May 2011 Reuters reported that the Imara
tribe had stopped work at West Qurna 2, but it didn’t say how. Then in March
2013 there was a demonstration, which got out of control with tribesmen
breaking into the field and smashing offices. Third, service contracts to start
drilling wells and other work at West Qurna 2 were signed very late. In
December 2011 Baker Hughes
International signed one deal, followed by Samsung
in March 2012. Drilling didn’t start until April
2012 as a result, a full year behind schedule. Finally, Statoil pulled out
of the deal. In February
2012 it said that it thought Iraq was too risky and that it wanted to
invest in other markets instead. The sale of its share was approved in March.
Companies like Lukoil and Statoil were originally attracted to Iraq because of
its huge untapped potential. It had large oil fields that had not been
developed for decades because of wars and sanctions. Businesses also knew there
were risks because Baghdad was unfamiliar with dealing with large international
corporations and its bureaucracy was infamous for being slow. Those problems
could account for the long time it took for the service contracts with Baker
Hughes and Samsung to be approved. The issue with mines should have been known
before hand as well, but the difficulties with local tribes and its business
partner Statoil pulling out could not be foreseen.
West Qurna 2 can be seen as a case study for why Iraq’s
lofty goals for its energy sector have always been behind schedule. Oil firms
rushed into Iraq because of its untapped potential, and agreed to production
goals that have proven to be unrealistic. There is still the issue of whether
the Oil Ministry will be able to install all of the infrastructure necessary to
export Lukoil’s production. That doesn’t mean Lukoil wont have West Qurna 2
eventually pumping large amounts of oil, but it is already two years behind its
original timeline, and it hasn’t overcome all of its difficulties. These are
the pros and cons of having to work in a developing country like Iraq.
SOURCES
Adel, Shaymaa,
“Russia’s Lukoil blamed for delay in bringing giant Iraqi oil field on stream
on time,” Azzaman, 12/13/13
Ajrash, Kadhim & Razzouk, Nayla, “Lukoil Pares Iraq
Oil-Output Target; Others Talk on Similar Cuts,” Bloomberg, 1/17/13
Bierman,
Stephen, “Lukoil Pumps Oil at Iraq’s West Qurna-2, Sees Sales by Year-End,”
Bloomberg, 10/25/13
Doroshev, Anton & Bierman, Stephen, “Lukoil to Boost
2013 Oil Output, Seek Extension to Iraq Contract,” Bloomberg, 1/15/13
Dow Jones, “Statoil Confirms Talks To Sell Stake In Iraqi
Oil Field,” 3/7/12
El Gamal, Rania, “Iraqi tribal disputes pose new challenge
to oil firms,” Reuters, 5/29/11
Gismatullin, Eduard and Stigset, Marianne, “Statoil May
Renegotiate West Qurna Contract, Questions Schedule,” Bloomberg, 6/23/11
Iraq-Business News, “Russian Lukoil to start drilling Iraqi
oil fields before the end of this year,” 3/22/10
Lando, Ben, “Roadblocks slow Lukoil, IOCs,” Iraq Oil Report,
4/7/11
Al-Mada,
“Lukoil postpone the start of oil production for the West Qurna-2 project to
next year,” 6/28/13
Mohammed, Aref, “Landmines hamper Iraq oil boom, delay
investment,” Reuters, 11/16/11
- “Protests heat up near Iraq’s West Qurna-2 oilfield,”
Reuters, 4/16/13
- “UPDATE 1-Iraq, Eni in talks to cut Zubair output to 1 mln
bpd,” Reuters, 1/29/13
- “UPDATE 2-Iraq West Qurna 2 output seen at 500,000 bpd in
2014,” Reuters, 4/25/12
- “UPDATE 3-Russia’s Lukoil begins output from giant Iraq
oilfield,” Reuters, 3/29/14
The National, “Iraq oil deals,” 12/12/09
Ostroukh, Andrey, “Lukoil to cut Iraq oil output 30% after
gov’t plan,” Wall Street Journal, 12/27/12
PanAremnian.Net, “LUKoil launches production drilling at
Iraqi West Qurna-2 oilfield,” 4/25/12
Radio Free Europe/Radio Liberty, “LUKoil Begins Pumping From
Major Oil Field Near Basra,” 4/25/12
Rasheed, Ahmed, “UPDATE 2-Statoil seeks Iraq’s OK to sell
oilfield stake,” Reuters, 2/2/12
Reuters, “Iraq’s West Qurna-1 oil field ‘a giant
challenge,’” 11/17/11
- “UPDATE 1-Iraq OKs $998 mln oil contract with
Samsung-source,” 1/24/12
RIA Novosti, “Lukoil May Start Production at West Qurna-2 in
2014,” Iraq Business News, 2/23/12
- “LUKoil to Invest $4 Bln in
Iraq’s West Qurna-2 in 2013,” 5/28/13
Salah, Khayoun, “Russia’s Lukoil says Iraq’s West Qurna to go
on stream end of year,” Azzaman, 3/5/13
Shiryaevskaya, Anna, “Lukoil to Boost Spending at Iraq Oil
Field to $2 Billion in 2012,” Bloomberg, 3/11/12
Soldatkin,
Vladimir and Golubkova, Katya, “UPDATE 2-Lukoil to launch Iraqi field by April,
double foreign oil output,” Reuters, 11/27/13
UPI, “Russia’s Lukoil starts demining in Iraq,” 9/21/10
No comments:
Post a Comment