In June 2004, the Coalition Provisional Authority authorized the construction of a wastewater treatment plant in the city of Fallujah in Anbar province. It was given special priority because Fallujah had just been devastated by a major battle between U.S. Marines and insurgents, and the Americans were hoping the plant would help win over the residents. Instead, the plant ran into delays, funding shortages, and attacks that greatly affected its completion. Today, the plant is operating, but only covers a fraction of the population it was originally supposed to, and it’s estimated that it still needs years more work to be completed. Fallujah’s wastewater project went from a centerpiece of the U.S. reconstruction effort in Iraq, to a symbol of its failure.
The hanging of American security contractors in March 2004 led to the first Battle of Fallujah (NoGW) |
Before that, Fallujah lacked a sewage system that serviced the entire city. Previously, residents had two ways to store and get rid of their waste water. One was that it was put into holding tanks that were then emptied out by trucks, and the other was a series of septic tanks that emptied out into the Euphrates River. This led to the contamination of not only the river, but the local drinking water as well. When the insurgency took off, this system began breaking down as militants stopped the septic trucks from operating and emptying the tanks. Those tanks began overflowing, leading to sewage flowing out into the streets.
In the summer of 2004, the CPA set out to begin the waste water treatment system for Fallujah. On June 26, the CPA signed a $28.6 million contract with Fluor AMEC to build the plant. It was given 18 months, until February 2006, to finish. The plan was for the water system to serve the entire city, and solve the problems of sewage in the streets, and the contamination of the Euphrates. The company immediately ran into problems. First, the insurgents had quickly taken back control of the city after the first Battle of Fallujah. That meant Fluor AMEC could not do site surveys to effectively plan out their work. They also had to ship in supplies from Baghdad through insurgent held territory. By October, the Marines in charge of Anbar halted work on the project in anticipation of the second Battle of Fallujah that started in November. The city was again destroyed, and the water system along with it. U.S. forces considered the latest operation a victory, but there were still insurgents in the city, and many relocated to Mosul, only to return later. It was still too dangerous for Fluor AMEC, but the Marines okayed work to begin again anyway. Like the CPA, the U.S. forces were hoping that the water treatment plant would be a good follow up to the offensive to show that the Americans had the needs of the people in mind. The Marines also believed that all the work could still be completed in 18 months, like the original contract stipulated. That proved completely unrealistic.
Violence almost completely derailed the project. Attacks in Anbar increased after the second Battle of Fallujah, peaking in the middle of 2006 with almost 4,500 incidents in a 90-day period. Some of this was aimed at the water plant. Staff was kidnapped, materials were stolen, equipment was attacked, bombs were planted at the site, and workers were threatened, shot at, killed, and wounded. Even after the Anbar Awakening was formed in 2006, and the Surge started in 2007, attacks upon the project did not relent. In May 2009, for instance, three reconstruction officials were killed by a bomb after visiting the site. During all this, the Marines told the company they would not protect them, and they had to hire their own private security. U.S. forces would also often shut down work for security operations. This was a problem throughout the entire time the company was trying to build the water plant. U.S. officials planned for a benign environment in Iraq, and ended up with an insurgency and civil war. Despite that, they continued to issue orders and sign contracts as if everything was business as usual. The attacks upon the water plant made it nearly impossible to ever finish, especially not in the 18 months it was supposed to be completed in.
(Special Inspector General for Iraq Reconstruction) |
Work went ahead anyway, and the Americans ended up transferring control of the project to the Iraqis. In 2008, the U.S. Ambassador to Iraq Ryan Crocker was worried about the future of the water plant, and called for an audit. It found that the lack of security was causing massive delays, a ballooning of costs, and a reduction of how much of Fallujah the project was going to serve. In 2009, the U.S. began thinking about turning over the plant to the Iraqis, because it was such a hassle. Baghdad however, did not have the capacity to finish the work at the time. Despite that, on May 2, 2011, the city of Fallujah and the Anbar provincial government had an opening ceremony for the wastewater treatment facility. The plant began operating for the first time, but only one of the four sewage lines was working, and it did not cover all residents as originally planned. In July, the Electricity Ministry connected the plant to the service lines in Anbar, and the State Department eventually contracted a company to train locals on operating procedures. Some of this was simply for show, because work was not completed, and only a fraction of Fallujah was served by the plant. It was also a sign that the Americans were through with the project, and wanted the Iraqis to take responsibility for it.
The Fallujah plant has proven to be a symbol of the failure of the United States to rebuild Iraq. As of September 2011, the project has cost $107.8 million, almost four times more expensive than originally planned. Although it is operating, it only connects 6,000 homes, approximately 38,400 people out of a total of 100,000, roughly one third of the city. Work is still not complete, but now Baghdad is supposed to finish it. That will cost an estimated $87 million and three more years, plus there is no guarantee that the Iraqis are up to the task. The one positive is that the plant can be expanded to serve the entire city if the Iraqi government has the means. The fact that the CPA embarked on this path from the beginning is the real issue. A massive infrastructure project in one of the most violent cities in Iraq should have never been started in the first place. No successful construction can be carried out within an insurgent hotbed where security is a constant issue. The Americans pressed ahead anyway, because the deal always had a political dimension to it. The CPA was hoping that the wastewater plant could win hearts and minds of Iraqis. Instead, it became a target of militants, and has never met its original goals. This was the problem not only in Fallujah, but across Iraq. Instead of large programs, the United States should have done much smaller ones, in close coordination with Iraqi communities, so that it could meet their needs, and be something that local Iraqi governments could maintain afterward. Instead, the U.S. went ahead with what they wanted, which proved unrealistic, a huge waste of money, and cost the lives of people that might not have lost them if not for the hubris of American officials.
SOURCES
Byman, Daniel, “An Autopsy of the Iraq Debacle: Policy Failure or Bridge Too Far?” Security Studies, October 2008
Davidson, Amy, “How Iraq Came Undone,” New Yorker, 11/15/04
Hamilton, Eric, “The Fight for Mosul,” Institute for the Study of War, 4/29/08
Kagan, Kimberly, “The Anbar Awakening: Displacing al Qaeda from Its Stronghold in Western Iraq,” Institute For The Study of War and Weekly Standard, 8/21/06-3/30/07
Rosen, Nir, “Home Rule,” New Yorker, 7/5/04
Special Inspector General for Iraq Reconstruction, “Falluja Waste Water Treatment System: A Case Study in Wartime Contracting,” 10/30/11
Thomas Ricks, Fiasco, New York: Penguin Press, 2006
5 comments:
Excellent report.
That is exactly what happens when there is either no planning, poor planning, or catastrophic planning under such adverse and challenging circumstances.
The summary, in fact, accurately and reasonably describes each step, cost, cost increase, and failure.
The problem, so often, was compounded by the ever-changing cast of characters, each under pressure to deliver on the ill-conceived projects of the last, no matter how troubled or inappropriate.
Note that during 2008, the brief window when civilian experts were on scene, Ambassador Crocker sought an audit, but, then the next crew came in....
An oft repeated story.
Steve wrote: "The problem, so often, was compounded by the ever-changing cast of characters, each under pressure to deliver on the ill-conceived projects of the last, no matter how troubled or inappropriate."
This affected so many things in Iraq, not just reconstruction projects. Things like the training of Iraqi forces, security operations, and U.S. strategy were also impacted.
I truly like to reading your post. Thank you so much for taking the time to share such a nice information.
This substance also known as water, is one of the most essential elements to health and is so important that your body actually has a specific drought management system in place to prevent dehydration and ensure your survival. Water might be everywhere, but one must never take it for granted. Thanks, this blog is very helpful.
Our squad of Sappers was sent to the Fallujah Waste Water Plant to find out how to "fix" it back in 03... What the hell do we know. We're not that kind of Engineer, let me know when you want us to blow it up. Did get some cool pictures sitting in front of all the... buttons. Like the Wizard of Oz or something.
Post a Comment